KARACHI, Nov. 26 (Focus Pakistan) – Karachi Industrial Park, which occupies 6,409 acres of Pakistan Steel Mills land, received Special Economic Zone status on Nov. 24.
The federal government is now considering an interim appointment of Pakistan Industrial Development Corporation (PIDC) as the project's lead developer, Business Recorder reported on Thursday.
Work on a 557-acre portion of the industrial park has already crossed the halfway mark. Prospective investors have submitted letters of intent for 88% of the industrial plots in this block.
The government aims to complete development work on the block by June 2027.
Karachi Industrial Park Needs Additional Funding
The approved development cost of the 557-acre site, known as Block A, stands at Rs7.404 billion. Physical progress has reached 52%, while financial progress stands at 31%. The project requires another Rs796.63 million in funding.
Also Read:Islamabad Seeks 1,000 Acres for Mega Industrial Zone to Attract Foreign Investors
Block A accounts for less than 9% of the total land earmarked for the industrial park. The June 2027 deadline covers this block alone.Interest from prospective industrial investors has come well ahead of the completion of development work. However, the letters of intent do not constitute final plot purchases.
The government plans to give PIDC responsibility for leading the development of the industrial park on an interim basis. The corporation's proposed appointment follows the Nov. 24 notification granting the project Special Economic Zone status.
The government has yet to announce a final decision on PIDC's appointment. The industrial park occupies land belonging to Pakistan Steel Mills near Port Qasim, one of the country's principal centres of industrial and maritime activity. The location gives prospective manufacturers access to an established industrial area and nearby port facilities.
A New Chapter for Pakistan Steel Mills Land
The development of Karachi Industrial Park concerns the industrial use of Pakistan Steel Mills land rather than the revival of steel production at the enterprise.
For prospective investors, much will depend on when the developers complete the infrastructure and make industrial plots available for manufacturing.
The available project details do not specify how much private investment the industrial park could attract or how many jobs it could generate. Nor do they provide a completion date for the remaining 5,852 acres.
For now, the government's immediate development target remains the 557-acre Block A, where construction has reached 52% and prospective investors have expressed interest in most of the available industrial plots.
Industrial Park Separate From Steel Mills Revival
The industrial park's development remains separate from efforts to revive Pakistan Steel Mills' steel production operations.
While the project seeks to utilise the enterprise's land for industrial development, it does not represent the restoration of its steel manufacturing facilities.
The June 2027 completion target also applies specifically to Block A rather than the entire 6,409-acre industrial park.
The project's success will ultimately depend on the government's ability to complete infrastructure development, secure financing and convert investor interest into operational industrial units.