PESHAWAR, Nov. 23 (Focus Pakistan) — : Pakhtunkhwa Energy Development Organization (PEDO) has applied to the National Electric Power Regulatory Authority (NEPRA) for an electric power supply licence for its Jabori Hydel Power Plant in Mansehra, which would let it sell electricity to industrial consumers, according to a public notice.
NEPRA has registered the application and invited comments in
favor or against from stakeholders, affected persons and the general public. Comments
must reach the Registrar's office within 15 working days of publication. The
regulator clarified that registration of the application is not approval of the
licence.
PEDO holds a generation licence (No. GL(Hydel)/15/2020)
dated April 29, 2020 for its 10.824MW plant on River Siran in Tehsil Baffa. It
has applied under Section 23E of the NEPRA Act read with Regulation 4 of the
Licensing (Electric Power Supplier) Regulations, 2022, and intends to supply
Bulk Power Consumers (BPCs).
PEDO has stated that the complex is already operational and
connected to the national grid at Battal through a dedicated indigenous 132KV
transmission line. Both direct supply and wheeling can be arranged for the
proposed consumers on the existing interconnection, with no technical changes
required.
The Khyber Pakhtunkhwa government completed the project,
which is expected to feed 71.1 GWh a year into the national grid. It is also
expected to earn the province Rs405 million annually. Jabori is one of three provincial
projects with a combined capacity of 63MW, along with the Koto plant in Dir and
Karora in Shangla, that have begun generating electricity.
Jabori Power Plant
The Jabori power plant is a 10.2 MW run-of-river
hydroelectric power plant located on the Siran River near Jabori in the
Mansehra District of Khyber Pakhtunkhwa, Pakistan. Developed by the Pakhtunkhwa
Energy Development Organization (PEDO) and funded by the provincial government,
it generates roughly 71.1 GWh of electricity annually for the national grid.
The move is not PEDO's first attempt to sell power directly
to industry. It has been selling electricity from its 18MW Pehur plant in Swabi
to five BPCs under the wheeling regime, using the distribution system of
Peshawar Electric Supply Company (Pesco). In October 2024, it applied to NEPRA
for a supply licence to serve units in the Gadoon Amazi Industrial Estate from
Pehur.
Also Read: NEPRA Removes K-Electric From DHA City Karachi Power Purchase Deal
The application comes as the market opens up. PEDO has
invited pre-qualification applications for supply from its hydropower plants
under a direct supply model and the competitive market framework. In September,
uniform grid charges for bulk consumers were approved, paving the way for a
400MW auction.
For industrialists battling high grid tariffs, a locally
generated and regulated source of electricity could prove attractive. Neither
the proposed consumers nor the tariff has been named in the notice.